An estimate assumptions register for uncertain service work

An estimate assumptions register lists the unverified conditions behind a proposed scope, their possible impact and how they will be checked. Use it before commitment so uncertainty is visible. It complements the estimate; it is not permission to add charges or change agreed work.

Copy the register

AssumptionDetails
Existing substrate is sound

Evidence needed: Inspection before installation

Impact if false: Different preparation may be needed

Owner and decision point: Site lead, before final scope

Customer can provide access

Evidence needed: Confirmed access window

Impact if false: Proposed date may not work

Owner and decision point: Coordinator, before booking

Specified part is available

Evidence needed: Supplier confirmation

Impact if false: Alternative needs review

Owner and decision point: Buyer, before ordering

Work an uncertainty through to a decision

Fictional example: a flooring estimate assumes a dry, sound base. Inspection finds damage. Change the assumption status to “disproved”, attach the inspection evidence and pause the affected scope decision. Describe the alternative preparation separately for review. Do not silently replace the original estimate or let the delivery team treat an unapproved option as agreed work.

Close the loop before handoff

Give every row a status: unverified, confirmed, disproved or no longer relevant, with date and evidence. Separate an assumption from an exclusion: an exclusion says what the offer does not include. Before handoff, highlight any unresolved condition and its agreed handling. If scope has already been accepted, use the change process rather than rewriting history.