Turn project acceptance criteria into a checkable matrix

Make acceptance criteria testable by linking each agreed requirement to a check, expected outcome, reviewer and evidence. Separate pass, fail and blocked results. Completion of a task list does not prove that the customer’s agreed requirements were met.

A worked acceptance matrix

RequirementDetails
Enquiry reaches correct team

Check: Submit a labelled test enquiry

Expected outcome: One record with the correct owner

Recorded result: Pass: reference TEST-18

Customer can correct an error

Check: Submit missing contact details

Expected outcome: Clear message; valid answers preserved

Recorded result: Fail: description erased

Authorised customer reviews handover

Check: Open restricted delivery link

Expected outcome: Only intended reviewer can access

Recorded result: Blocked: reviewer unavailable

Make the evidence meaningful

The rows above are fictional examples, not a test report for Client Craft. In your own matrix, record the version, environment, date and person running the check. Evidence can be a record reference, measurement or authorised screenshot. Avoid “works well” as an expected result: it does not tell a reviewer what to observe. Use a separate row when a requirement has materially different success and failure conditions.

Handle exceptions without relabelling them

Assign failed checks an owner and correction plan. A blocked check stays blocked until its prerequisite is available; it is not a pass. If the customer accepts a known limitation, record the precise exception, affected requirement and decision separately. Recheck only the corrected behaviour and affected dependencies. This worksheet organises operational evidence; it does not replace contractual acceptance terms.

Keep a failed result alongside its later passing recheck, linked by the same requirement, so the correction remains traceable.